Attending the ceremony has the leaders: Mr. Luu Xuan Vinh, Deputy Secretary of the Provincial Party Committee, Chairman of the Provincial People's Committee and Mr. Pham Van Hau, Vice Chairman of the Provincial People's Committee.
The project of Sinenergy Ninh Thuan I solar power plant combining with Hi-tech agriculture has a capacity of 50MWp with total investment capital of VND1,319 billion. It is implemented in Phuoc Huu commune (Ninh Phuoc) in an area of 60ha. The duration of project operation is 50 years as of the date of decision issuance on investment policy. The progress of the project lasts 18 months, of which:
+ From January to June, 2018: Completing relavant legal procedures;
+ July, 2018 : Starting the project;
+ From August 2018 to February 2019: Completing the construction of the main works, including: transformer stations, operators, internal roads and the foundation of installing the battery panels;
+ From March 2019 to May 2019: Completing installation of equipment (energy panels, machinery and test run);
+ By June 2019: The whole project will be completed and connected to the national grid.
Speaking at the ceremony, the Chairman of the provincial People's Committee requested the investor to urgently complete the project related procedures, especially signing the secured funding of investment project implementation, the establishment of enterprise in the province, and procedures for land, construction, purchase of electricity. and so on. In the course of implementation, it is required to comply with the regulations on environmental protection, fire prevention and fighting and other relevant laws. The province will direct the departments, branches and localities to coordinate, support, create favorable conditions for investors to implement the project to ensure the schedule as stated in the decision.
Mr. Ng Han Kok, representative of investor expressed thanks for the concern and trust of the provincial People's Committee and pledged to concentrate all resources, personnel, experience and finance to deploy the next steps in order to put the project into operation soon.
For more information on investment opportunities in Vietnam, visit our homepage
Source: Ninh Thuan News