The solar project will be connected with the power system by a generator step up transformer with a capacity of 63MVA and voltage of 22/110kV, and a 110kV single transmission line from the project to Cam Lien 110kV transformer substation with a length of 6.5km. These components expect to be operated by 2019.
MOIT requires Dohwa group in cooperation with Quang Binh People’s Committee, Electricity of Vietnam (EVN) and EVN Central Power Corporation to be responsible to mobilize the capital and invest in items added in the planning in accordance with the schedule and ensure the safe electricity supply. MOIT also requires the investor to be responsible for project investment efficiency and comply with the electricity price under Prime Minister’s Decision No 11/2017/QĐ-TTg
The total project expects to be completed at the end of 2018 and beginning of 2019.
For more information on investment opportunities in Vietnam, visit our homepage
Source: Vietnam Energy Online